Please use the below scope of work to complete the google form linked on this page
Scope of Work:
Mill & Pave 4" Depth (Blue)
1. The area under consideration comprises approximately 8,134 square feet. (see map for area highlighted blue)
2. Mill pavement to the depth of 4 Inches.
3. All repairs to be shaped symmetrically where possible.
4. Millings and debris will removed from job site area and hauled to proper recycling center. Work area will then be swept and blown clean.
5. Install 2.5 inches of compacted thickness asphalt leveling course
6. Apply asphalt bond coat SS-1H evenly on all surfaces to be paved.
7. Install 1.5 inches of compacted thickness surface asphalt
8. All areas will be barricaded during and after the repair process.
Restriping:
Restripe lot to existing layout
Submit Bids by: 05/25/2025